Schedule Update

1/16/2024

 
Picture
Work update | January 16, 2024
  • The Steel erection and detailing at visual mockup was completed.
  • The geopiers ground improvements were completed.
  • The installation of the storm and sewer from loading dock to Fairmont started.
  • The partial installation of the storm and sewer from loading dock to lower section access road was completed.
  • The temp water service at top of the berm was completed.
  • The lagging at piles including walers and tie backs was substantially completed.
  • The concrete subcontractor mobilized to the site and the first mud mat was placed.
  • The footings and walls installation commenced including waterproofing and sleeves.